Design of Vibration Isolation for a 350 ton press at Olympic factory

Design of Vibration Isolation for a 350 ton press at Olympic factory:

Project location: Egypt.
CLIENT: Olympic Group
Scope of work:
Olympic factory was installing two new presses; the presses have a repeated force action = 250 knock per hour. The supplier provided drawings for the reinforced concrete foundation indicating that a vibration isolation layer should be installed beneath the concrete layer. The objective of the project was to design and supervise the installation of this vibration isolator.

Design of Vibration Isolation
36 Isolation patches installation